The maintenance has been completed since approximately 22:05. We have checked all VMs and servers for operational status. We are continuing to monitor our infrastructure.
Posted Aug 17, 2024 - 23:38 CEST
Update
We are currently experiencing issues with the planned maintenance with two hypervisors. Our technicians currently looking into it and we will provide an update here shortly.
Posted Aug 17, 2024 - 22:12 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 17, 2024 - 22:00 CEST
Scheduled
Our data center provider MK Netzdienste has scheduled a power maintenance for this Saturday starting at 22:00. The maintenance is scheduled to last about five minutes. Due to our redundancy concept we don't expect any downtime in our infrastructure. The power maintenance will be covered by UPS and generator.
If you have any questions, please feel free to contact us at support@lumaserv.com.
Posted Aug 14, 2024 - 15:48 CEST
This scheduled maintenance affected: Infrastructure (FRA14, Interxion) (Power Supply).